Case Study

Project Type: Commercial
Software Used: Civil 3D, AutoCAD, Google Earth
Project Duration: 50 hours
Task Assigned
The client assigned us multiple civil tasks, including Site Plan Development, Grading & Drainage Plans, Utility Plan, Erosion & Sediment Control Plan, and Paving Plan.

Project Timeline
- Phase 1 – Layer translation of survey file
- Phase 2 – Create master file, manage layer states, and prepare site and demolition plans
- Phase 3 – Finalize the plan with the client

Additional Note
- Translating survey layers was challenging, as each line was assigned to a separate layer, making it hard to remember. Our team created an individual, organized list of layers.
- Managing the layer state was complex. We assigned each plan its own layer settings, enabling and disabling layers as needed.